2.The 34m span bridge members pre-assembled in McIntosh factory to ensure site work was kept to a minimum |
3.The slotting and drilling for the brackets was done before delivery to site. |
4.Kelvin Landon from LHT says, “we enjoyed working closely with McIntosh Timber Laminates Ltd, ensuring the structure was simple to build, cost-effective & in-line with the client’s needs. The structural frame of the bridge curves in differing directions, creating a crossing that carries the required load, but also has a soft visual impact.” |